Factors Causing Delay in Jordan Public Road/Highway Projects

Omar Saleh Alhawatmeh, Salman Riazi Mehdi Riazi, Mohd Wira Mohd Shafiei

http://dx.doi.org/10.6007/IJARAFMS/v13-i1/16152

Open access

Project delays are an incessant dilemma haunting the construction industry worldwide and Jordan is of no exception especially with their public road/highway construction projects. This is not healthy as proper delivery of these infrastructures are vital for the citizens and country’s development. This paper presents part of an-going research at developing a framework for delay mitigation in Jordan’s public road/highway construction projects. The project at focus were public road/highway projects valued up to JD 210,000.00. Qualitative technique in form of interviews was conducted on 27 Jordanian industry professionals with a minimum of 10 years’ relevant experiences. They were asked to assess the significant reason for delay in Jordanian public road/highway construction projects. Data analysis was conducted using Nvivo software resulting to the identification of 54 factors which were divided into 14 categories. Findings established Scheduling Related factors as the most significant reasons of delay followed by Change Related factors. On the other hand, three (3) categories were the least significant namely Financial Related factors, Decision Related factors, and Motivation Related factors. Findings from this study could assist Jordan practitioners to better understand the potential delay contributors in similar future projects and hence, strategize effective mitigation and control plans.

Abas, M., Khattak, S. B., Habib, T., & Nadir, U. (2020). Assessment of critical risk and success factors in construction supply chain: a case of Pakistan. International Journal of Construction Management, 1-9.
Abd El-Razek, M. E., Bassioni, H. A., & Mobarak, A. M. (2008). Causes of delay in building construction projects in Egypt. Journal of construction engineering and management, 134(11), 831-841.’
Abdullah, M. R., Rahman, I. A., & Azis, A. A. A. (2009). Delay in large MARA construction projects based on project management consultant perspective. In Proc. Malaysian Technical Universities Conference on Engineering and Technology (pp. 9-13).
Aibinu, A. A., & Odeyinka, H. A. (2006). Construction delays and their causative factors in Nigeria. Journal of construction engineering and management, 132(7), 667-677.
Al-Adwani, M. M., Mollasalehi, S., & Fleming, A. J. (2018, December). A study of root causes of delays in the public-sector construction projects in Kuwait. In Proceedings, International Conference on Construction Futures (ICCF). University of Wolverhampton.
Alaghbari, W. A. M. (2005). Factors affecting construction speed of industrialized building systems in Malaysia (Unpublished master’s thesis). University Putra Malaysia, Serdang, Malaysia.
Al-Hazim, N., & Salem, Z. A. (2015). Delay and cost overrun in road construction projects in Jordan. International Journal of Engineering & Technology, 4(2), 288.
Al-Hazim, N., Salem, Z. A., & Ahmad, H. (2017). Delay and cost overrun in infrastructure projects in Jordan. Procedia Engineering, 182, 18-24.
Alkass, S., Mazerolle, M., & Harris, F. (1996). Construction delay analysis techniques. Construction Management and Economics, 14(5), 375-394.
Al-Khalil, M. I., & Al-Ghafly, M. A. (1999). Important causes of delay in public utility projects in Saudi Arabia. Construction Management & Economics, 17(5), 647-655.
Al?Kharashi, A., & Skitmore, M. (2009). Causes of delays in Saudi Arabian public sector construction projects. Construction Management and Economics, 27(1), 3-23.
Al-Sultan, A. S. (1987). Determination of construction contract duration for public projects in Saudi Arabia (Unpublished master’s thesis). King Fahd University of Petroleum & Minerals, Dhahran, Saudi Arabia.
Assaf, S. A., & Al-Hejji, S. (2006). Causes of delay in large construction projects. International journal of project management, 24(4), 349-357.
Assaf, S. A., Al-Khalil, M., & Al-Hazmi, M. (1995). Causes of delay in large building construction projects. Journal of management in engineering, 11(2), 45-50.
Atran, S., Medin, D. L., & Ross, N.O. (2005). The cultural mind: Environmental decision making and cultural modeling within and across populations. Psychological Review, 112(4), 744-776.
Bekr, G. A. (2018). Study and assessment of causes and effects of delay in large public construction projects in Jordan. International Journal of Applied Engineering Research, 13(8), 6204-6210.
Braun, V., & Clarke, V. (2006). Using thematic analysis in psychology. Qualitative research in psychology, 3(2), 77-101.
Btoush, M., & Harun, A. T. (2017, November). Minimizing delays in the Jordanian construction industry by adopting BIM technology. In IOP Conference Series: Materials Science and Engineering (Vol. 271, No. 1, p. 012041). IOP Publishing.
Chan, D. W., & Kumaraswamy, M. M. (1997). A comparative study of causes of time overruns in Hong Kong construction projects. International Journal of project management, 15(1), 55-63.
Dixit, S., Mandal, S. N., Thanikal, J. V., & Saurabh, K. (2019). Evolution of studies in construction productivity: A systematic literature review (2006–2017). Ain Shams Engineering Journal, 10(3), 555-564.
Fong, C. K. (2004). Law and practice of construction contracts (3rd ed.). Singapore: Sweet & Maxwell Asia.
Frimpong, Y., Oluwoye, J., & Crawford, L. (2003). Causes of delay and cost overruns in construction of groundwater projects in a developing countries; Ghana as a case study. International Journal of project management, 21(5), 321-326.
Guest, G., Bunce, A., & Johnson, L. (2006). How many interviews are enough? An experiment with data saturation and variability. Field Methods, 18(1), 59-82.
Honigmann, J. J. (1982). Sampling in ethnographic fieldwork. In R. G. (Ed.), Field research: A sourcebook and field manual (pp. 79-90). London: Allen & Unwin.
Islam, M. S., & Trigunarsyah, B. (2017). Construction delays in developing countries: a review. Journal of Construction Engineering and Project Management, 7(1), 1-12.
Kaming, P. F., Olomolaiye, P. O., Holt, G. D., & Harris, F. C. (1997). Factors influencing construction time and cost overruns on high-rise projects in Indonesia. Construction Management and Economics, 15(1), 83-94.
Long, N. D., Ogunlana, S., Quang, T., & Lam, K. C. (2004). Large construction projects in developing countries: a case study from Vietnam. International Journal of project management, 22(7), 553-561.
Mason, M. (2010). Sample size and saturation in PhD studies using qualitative interviews. In Forum qualitative Sozialforschung/Forum: qualitative social research (Vol. 11, No. 3).
Riazi, M. S. R. (2014). The use of supply chain management to reduce delays as result of pre-construction deficiencies in Malaysian public sector construction projects (Doctoral dissertation, Queensland University of Technology).
Miles, M. B., & Huberman, A. M. (1994). Qualitative data analysis: An expanded sourcebook. sage.
Morse, J. M. (1994). Designing funded qualitative research. In N. K. Denzin & Y. S. Lincoln (Eds.), Handbook of qualitative research (pp. 220-235). Thousand Oaks, CA: Sage.
Mpofu, B., Ochieng, E. G., Moobela, C., & Pretorius, A. (2017). Profiling causative factors leading to construction project delays in the United Arab Emirates. Engineering, Construction and Architectural Management.
Msallam, M., Abojaradeh, M., Jrew, B., & Zaki, I. (2015). Controlling of variation orders in highway projects in Jordan. Journal of Engineering and Architecture, 3(2), 95-104.
Muhwezi, L., Acai, J., & Otim, G. (2014). An assessment of the factors causing delays on building construction projects in Uganda. International journal of construction engineering and management, 3(1), 13-23.
Narayan, S., & Tan, H. C. (2019). Adopting big data to forecast success of construction projects: A review. Malaysian Construction Research Journal, 6(1), 132-143.
Odeh, A. M., & Battaineh, H. T. (2002). Causes of construction delay: traditional contracts. International journal of project management, 20(1), 67-73.
Odeyinka, H. A., & Yusif A. (1997). The causes and effects of construction delays on completion cost of housing project in Nigeria. Journal of Financial Management of Property and Construction, 2, 31–44.
Ogunlana, S. O., Promkuntong, K., & Jearkjirm, V. (1996). Construction delays in a fast-growing economy: comparing Thailand with other economies. International Journal of project management, 14(1), 37-45.
Patton, M. Q. (2014). Qualitative research & evaluation methods: Integrating theory and practice. Sage publications.
Prokhorov, V. I. (2018). Calculation method of heat consumption for buildings life support systems. In IOP Conference Series: Materials Science and Engineering (Vol. 365, No. 2, p. 022023). IOP Publishing.
Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of project management, 25(5), 517-526.
Sar?kaya, O. (2010). Causes of delay in and their effects on construction projects in Turkey. Bogazici Universitesi.
Senouci, A., Ismail, A., & Eldin, N. (2016). Time delay and cost overrun in Qatari public construction projects. Procedia engineering, 164, 368-375.
Strauss, A., & Corbin, J. (1998). Basics of qualitative research techniques.
Sweis, G., Sweis, R., Hammad, A. A., & Shboul, A. (2008). Delays in construction projects: The case of Jordan. International Journal of project management, 26(6), 665-674.
Turner, D. F. (1989). Building contracts disputes - Their avoidance and resolution. London: Longman.
Zain Al-Abedien, H. M. (1983). About the effect of delay penalty on the construction of projects and modification proposals. In Proceedings of the First Engineering Conference (pp. 14-19).
Zidane, Y. J. T., & Andersen, B. (2018). The top 10 universal delay factors in construction projects. International Journal of Managing Projects in Business.

In-Text Citation: (Alhawatmeh et al., 2023)
To Cite this Article: Alhawatmeh, O. S., Riazi, S. R. M., & Shafiei, M. W. M. (2023). Factors Causing Delay in Jordan Public Road/Highway Projects. International Journal of Academic Research in Accounting Finance and Management Sciences, 13(1), 209–223.