Cost Performace of Road Construction Projects in Nigeria

Victor Imohnikhe Aligamhe, Muzani Mustapa, Chukwuemeka Patrick Ogbu

http://dx.doi.org/10.6007/IJARAFMS/v14-i1/20783

Open access

The construction of highways requires huge capital; therefore, to meet their performance goals, a significant amount of resources and meticulous preparation are needed. The study investigates the magnitude and causes of cost overruns in highway construction projects. A review of existing literature was conducted, followed by a focused group meeting to identify the cost-risks related to the construction of highway projects in Nigeria. Historical cost data on highway projects published by the Nigerian FMWH in 2017 served as a preliminary list of projects for the study, while cost data of more completed projects was gotten from highway engineers and quantity surveyors across Nigeria using the snowballing technique until 103 highway projects were identified. Major project participants were purposively chosen to fill out questionnaires on cost-risk factors associated with highway construction projects. The collection of primary data (risk factors) and secondary data (cost performance) was done simultaneously. The mean score (MS) and the severity of each of the factors were computed, while Pareto’s rule was used to determine the significant risks. To determine the cost performance of the completed highway projects, the cost deviation of each identified project as well as the mean deviation of the total projects were calculated. The study identified six significant cost risks affecting federal highway projects in Nigeria. Further, findings revealed that Nigeria’s federal highway projects have a mean cost overrun of 31.36%, and the probability of cost occurrence is 94.14%. Finally, findings show that 60% of federal highway projects in Nigeria experience very high cost overruns (of over 20 %), with their attendant effect on other project objectives.

Abdul Rahman, I., Hameed, M. A., & Abd.- Karim, T. A. (2013) “Significant factors causing cost overruns in large construction projects in Malaysia. Journal of Applied Sciences, 13(2), pp. 286–293
Ahmed, A., Kayis, B., & Amornsawadwatana, S. (2007). A review of techniques for risk management in projects. Benchmarking: An International Journal, 14(1), pp.22-36
Aibinu, A., & Jagboro, G. (2002). The effects of construction delays on project delivery in Nigerian construction industry. International. Journal of Project. Management. 20, pp. 593–599
Akoh, S. R. W. (2018). Risk Management Framework for Highway Construction Projects In Nigeria. Heriot-Watt University School of Energy, Geosciences’ Infrastructures and Society, Edinburgh-United Kingdom: Ph.D. Thesis
Al-Hazim, N., & Salem, Z. A. (2015), Delay and cost overrun in road construction projects in Jordan. International Journal of Engineering and Technology, 4( 2), pp. 288-293
Alinaitwe, H., Apolot, R., & Tindiwensi, D. (2013). An investigation into the causes of delay and cost overrun in Uganda's public-sector construction projects. Journal of Construction in Developing Countries, 18(2), pp. 33-47
Ammar, T., Abdul-Momen, M., El-Dash, K., & Shams, A. (2022). Risk factors causing overruns in road networks. Ain ShamsEngineering Journal. 13 (5). Retrieved October 30, 2023, from https://dci.org/10.1016/j.asej.2022.101720
Awuku, B., Asa, E., Baffoe-Twum, E., & Essegbey, A. (2022). Conceptual cost estimation of highway bid items – A systematic literature review. Engineering, Construction and Architectural Management. DOI 10.1108/ECAM-03-2022-0266
Bhangale, P. P. (2016). Analysis of time and cost overrun to the key success of high-rise commercial building project-A case study. International Journal of Civil Engineering and Technology (IJCIET), 7(4), pp. 400–405
Borse, M., & Khare, P. (2016). Analysis of cost and schedule overrun in construction projects. International Journal of Innovative Science, Engineering & Technology (IJISET), 3(1), pp. 383-386
Bowers, J., & Khorakian, A. (2014). Integrating risk management in the innovation project. European Journal of Innovation Management, 17(1), pp. 25-40
Chitkara, K. K. (2009). Construction project management–Planning, scheduling and controlling. New Delhi: Tata McGraw-Hill Publishing Company Limited
Creedy, G. D., Skitmore, M., & Wong, J. (2010). Evaluation of risk factors leading to cost overrun in delivery of highway construction projects. Journal of Construction Engineering and Management. 136(5), pp. 528-536
Danisworo, B., & Latief, Y. (2019). Estimation model of Jakarta MRT phase 1 project cost overrun for the risk based next phase project funding purpose. IOP Conf. Ser.: Earth Environ (ICoSITeR) 2018. Sci. 258 012049.
Ekung, S., Adeniran, L., & Adu, E. (2015). Theoretical risk identification within the Nigeria east- west coastal highway project. Civil engineering and urban planning. An International Journal (CiVEJ). 2(1), pp. 1-11
Elinwa, U. A., & Buba, S. A. (1994). Construction cost factors in Nigeria. Journal of Construction Engineering and Management, 119(4), pp. 698-713
El-Sayegh, S.. & Mansour, M. (2015). Risk assessment and allocation in highway construction projects in the UAE”, Journal of Management. in Engineering. 31(6). pp. 04015004 - 1- 04015004-11
Enshassi, A., Al-Najjar, J.. & Kumaraswamy, M. (2009). Delays and cost overruns in the construction projects in the Gaza Strip. Journal of Financial Management, Property Construction. 14, pp. 126-151
Fabi, J. K. (2019). Risk Allocation Framework Development for Build-Operate-Transfer Highway Projects in Nigeria. Universiti Teknologi Malaysia: Ph.D. Thesis
Federal Ministry of Works and Housing. (2013). Compendium Report on Road Infrastructure and Related Development in Nigeria- An Investor´s Manual. Retrieved June 6th, 2022 from https://www.google.com/url?sa=t&rct=j&url=https://www.casafrica.es/caseafrica/newsletter/2017/compediueport_PPP_Nigeria.pdf&ved=2ahUKEwjJxZ320eD0AhUJQKHa5ZA_kQFnoECAMQAQ&usg=AOvVaw2xPXrQBfidUXOoUxWmLLtt
Flyvbjerg, B. (2017). The Oxford Handbook of Megaproject Management. Oxford University Press
Flyvbjerg, B., Bruzelius, N., Van Wu, B. (2008). Comparison of Capital Costs per route-Kilometer in Urban Rail. European Journal of Trnsportation Infrastructure Resources. 8(1), pp. 17-30
Flyvbjerg, B., Holm, S. M. K., & Buhl, S. L. (2003). How common and how large are cost overruns in transport infrastructure projects? Transport Reviews, 23(1), pp. 71-88
Ganiyu, B., & Zubairu, I. (2010). Project cost prediction model using principal component regression for public building projects in Nigeria. Journal of Building Performance,1(1), pp. 21-28
Gondia, A., Siam, A., El-Dakhakhni, W. & Nassar, A. H. (2019). Machine learning algorithms for construction projects delay risk prediction. Journal of Construction Engineering and Management, 146(1). Retrieved October 30, 2023, from
https://doi.org/10.1061/(ASCE)CO.1943-7862.0001736
Gransberg, D., & Buitrago, V. M. (2002). Construction project performance metrics. In AACE International Transactions; EBSCO Publishing: Ipswich, MA, USA, 2002; p. CSC.02
Grimaldi, S., Rafele, C., & Cagliano, A. C. (2012). A Framework to Select Techniques Supporting Project Risk Management (pp. 67-96). InTech.
Grosfeld-Nir, A., Ronen, B., & Kozlovsky, N. (2007). The Pareto managerial principle: When does it apply? International Journal of Production Research. 45(10). pp. 2317-2325
Heralova, R. S., Hromada, E., & Johnston, H. (2014). Cost Structure of the Highway Projects in the Czech Republic. Procedia Engineering. 85, pp. 222-230
Herrera, R. F., Sánchez, O., Castañeda, K., & Porras, H. (2020). cost overrun causative factors in road infrastructure projects: a frequency and importance analysis. Appl. Sci., 10, 5506 https://doi.org/10.3390/app10165506
Kovacevic, M., Ivanisevic, N., Petronijevic, P. & Despotovic, V. (2021). Construction cost estimation of reinforced and pre stressed concrete bridges using machine learning. Gra?evinar, 73(1), pp. 1-13
Leo-Olagbaye, F., & Odeyinka, H. A. (2020). An assessment of risk impact on road projects in Osun State, Nigeria”, Built Environment Projects and Asset Management. 10(5), pp. 673-69
Mahamid, I., Bruland, A., & Dmaidi, N. (2012). Causes of delay in road construction projects. Journal of Management in Engineering, 28(3), pp. 300–310
Memon, A. H., Rahman, I. A., & Aziz, A. A. A. (2012). The causal factors of large project’s cost overrun: A survey in southern part of Peninsular Malaysia. International Journal of Real Estate Studies, 7(2), pp. 1-15.
Moghayedi, A., & Windapo, A. (2018). Identification of the uncertain events impacting on construction time of South African highway projects. Journal of Construction Project Management and Innovation, 8(1), pp. 2146-2163
Nadir, H., & Ahmed, A. (2020). Causes and Monitoring of delays and cost overrun in construction projects in Pakistan. International Journal of Engineering Inventions, 9 (8). pp. 20-33. ISSN 2278-7461 International Journal of Engineering Inventions e-ISSN: 2278-7461, p-ISSN: 2319-6491 Volume 9, Issue 8 [August. 2020] PP: 20-33
Nicholas, J., & Steyn, H. (2012). Project management for engineering, business and technology. 6th Edition, Routledge
Nurdiana, A., Wibowo, M. A., & Kurnianto, Y. F. (2019). The identification of risk factors of delay on the road construction projects in Indonesia. Advances in Engineering Research, Vol 167. International conference on maritime and archipelago (ICoMA, 2018), Alantis Press. January, 2019. pp. 384-387.
Oboirien, M. O. (2019). Modelling Cost and Time Performance of Public Building Projects in a Terror Impacted Area of Nigeria. University of Cape Town, South Africa: Ph.D. Thesis
Odeck, J. (2019). Variation in Cost overruns of Transportation Projects: an econometric meta-regression analysis of Studies Reported in Literature. Transportation, Springer,46(4), pp. 1345 – 1368
Okafor, C. O. (2016). A critical assessment of road infrastructural development in Akwa-Ibom state, Nigeria. African Research Review: An International Multidisciplinary Journal, Ethiopia. 14 (1), pp. 179-193
Olatunji, O. A. (2008). A comparative analysis of tender sums and final costs of public construction and supply projects in Nigeria. Journal of Financial Management of Property and Construction. 13(1), 60-79
Oraegbune, O. M. (2008). Effects of project overrun on public construction projects (A case study of some selected projects in Adamawa State). Federal University of Technology, Yola Nigeria: MSc. Thesis
Pandey, V., Bairwa, A., & Bhattacharya, S. (2013). Application of the Pareto principle in rapid application development model. International Journal of Engineering and Technology. 5(3). pp. 2649-2654
Project Management Institutes (PM1), (2008). A Guide to the Project Management Body of Knowledge, 4th ed. Project Management Institute, Newton Square, PA.
Rizwan, M., & Igbal, M. (2011). Application of 80/20 rule in software engineering rapid application development (RAD). Model International Conference on Software Engineering and Computer System (ICSECS 2011), Springer, pp518-532
Robert, S. (1987). The Pareto principle: its use and abuse. Journal of Services Marketing, 1(2), pp. 37-40
Roslan, N., Zainun, N. Y., & Memon, A. H. (2015). Relevancy of factors and mitigation measures in controlling time and cost overrun towards Malaysian environment. Applied Mechanics and Materials, pp. 1007-1011. Retrieved October 30, 2023 from www.scientific.net/AMM.
Rwelamila, P. D., & Ogunlana, S. (2015). Construction in developing countries – Research roadmap report for consultation. In International Council for Research and Innovation in Building and Construction, Publication, 413, pp. 1-17
Shane, J. S., Molenaar, K. R., Anderson, S., & Schexnavder, C. (2009). Construction project cost escalation factors. Journal of Management in Engineering 25( 4), pp. 221-229
Sharaf, M. M. M., & Abdelwahab, H. T. (2015). Analysis of risk factors for highway construction projects in Egypt. Journal of Civil Engineering and Architecture. 9(6), pp. 26-533.
Shrestha, P. P., Burns, L. A., & Shields, D. R. (2013). Magnitude of construction cost and schedule overruns in public work projects. Retrieved October 30, 2023 from http://dx.doi.org/10.1155/2013/935978.
Stasiak-Betlejewska, R. (2015). Construction Costs Analysis and its importance to the economy. Procedia Economics and Finance, 34, pp. 35 - 42
Svenssson, G., & Wood, G. (2006). The Pareto plus syndrome in top marketing journal: Research and journal criteria, Euro. Business Review. 18(6), pp. 457-467
Thaseena, T., & Vishnu, K. (2017). Analysis of cost overrun in highway construction projects using multiple regression and artificial neural networks. International Research Journal of Engineering and Technology. 4(4). pp. 2332-2336
Wang, M., & Chou, H. (2003). Risk allocation and risk handling of highway projects in Taiwan. Journal of Management in Engineering 19(2). pp. 60-68
Wang, T., Wang, S., Zhang, L., Huang, Z., & Li, Y. (2016 ). A major infrastructure risk-assessment framework: Application to a cross-sea route project in China. International Journal of Project Management, 34(7), pp. 1403-1415
Zayed, T., Amer, M., & Pan, J. (2008). Assessing risk and uncertainty inherent in Chinese highway projects using AHP. International. Journal Project Management 26(4). pp. 408-419.

(Aligamhe et al., 2024)
Aligamhe, V. I., Mustapa, M., & Ogbu, C. P. (2024). Cost Performace of Road Construction Projects in Nigeria. International Journal of Academic Research in Accounting Finance and Management Sciences, 14(1), 365–381.