A Study of Using Simulation to Overcome Obstacles that Block the Implementation of Critical Chain Project Management to Project Management Environment

Chia-Ling Huang, Rong-Kwei LI, Chih-Hung Tsai, Yi-Chan Chung, Yao-Wen Hsu

http://dx.doi.org/10.6007/IJARAFMS/v4-i1/505

Open access

Since 1997, the Critical Chain Project Management (CCPM) method has received considerable attention. Hundreds of successful CCPM cases have achieved highly reliable on-time delivery (OTD) with short project lead-time (PLT) in multi-project environments. However, two obstacles have remained, blocking the implementation of CCPM to project management (PM) society. The first has been addressed by PM practitioners, who have been less than confident that OTD and PLT can be significantly improved by simply changing the way to manage multi-projects. The second is from academia: some scholars have claimed that the ideas of CCPM are not new and are of no substantial contribution to Project Management Body of Knowledge (PMBOK). In this study, we first used multi-project management games to overcome the first obstacle. A comparative study of CCPM and Program Evaluation and Review Technique/Critical Path Method (PERT/CPM) planning methods, excluding bad human behaviors, was then conducted to overcome the second obstacle. The simulation results show that: (1) the “mode of managing multi-projects” was the root cause, and changing the mode of managing multi-project could significantly improve OTD and PLT; (2) in terms of mean project time, CCPM is not significantly better than PERT/CPM. However, in terms of plan reliability, CCPM achieves higher than PERT and CPM. This is due to a CCPM logistical change that generates a more reasonable and reliable project plan than do the PERT/CPM methods.

Ashtiani, B., Jalali, G. R., Aryanezhad, M. B., Makui, A. (2007). A new approach for buffer sizing in Critical Chain scheduling. IEEE Conferences, Industrial Engineering and Engineering Management International Conference, Singapore, 1037-1041.
Cohen, I., Mandelbaum, A., and Shtub, A. (2004). Multi-Project scheduling and control: a process-based comparative study of the critical chain methodology and some alternatives. Project Management Journal, 35(2), 39-50.
Cui, N., Tian, W., and Bie, I. (2010). Rescheduling after inserting the buffer in the Critical Chain scheduling. IEEE Conferences, Logistics Systems and Intelligent Management International Conference, Harbin, 2, 1105-1110.
Drucker, P. F. (1985) Innovation and entrepreneurship. William Heinemann Ltd, England.
Duncan, W. R. (1999). Back to basics: charters, chains, and challenges. PM Network. Project Management Institute.
Elmaghraby, E., Herroelen, W. S., And Leus, R. (2003). Note on the paper ‘Resource-constrained project management using enhanced theory of constraint’ by Wei et al. International Journal of Project Management, 21, 301-305.
Goldratt, E. M. (1997a). Critical Chain. The North River Press Publishing Corporation, Great Barrington.
Goldratt, E. M. (1997b). Project Management the TOC Way. The North River Press Publishing Corporation, Great Barrington.
Goldratt, E. M., and Goldratt, A. R. (2003). TOC Insights-Project Management and Engineering. http://www.toc-goldratt.com/store/product.php?productid=16273, Accessed March 20, 2010.
Goldratt, E. M. (2008) Standing on the shoulders of giants-production concepts versus production applications. TOCICO International Conference, Las Vegas, Nevada.
Goldratt, E. M. (2009). The Strategy and Tactic Tree for Projects. https://tocico.site-ym.com /default.asp?page=s_and_t, Accessed March 20, 2010.
Goldratt Marketing Group. (2011). http://www.toc-goldratt.com
Herroelen, W., and Leus, R. (2001). On the merits and pitfalls of critical chain scheduling. Journal of Operations Management, 19 (5), 559-577.
Herroelen, W., Leus, R., and Demeulemeeter, E. (2002) Critical chain project scheduling: Do not oversimplify. Project Management Journal, 33(4), 48-60.
Jacob, D., and Mendenhall, B. (2008) Project Management in a Lean World. TOCICO International Conference, Las Vegas, Nevada.
Kapoor, A. (2009). Why Lean doesn’t work. Execution Management Minute Realization Company, USA.
Leach, L. P. (1999). Critical Chain Project Management improves project performance. Project Management Journal, 30(2), 39-51.
Leach, L. P. (2004). Critical Chain Project Management. Artech House Publishers.
Liu, J. B., and Xie, J. H. (2008). Critical Chain Project Management based heuristic algorithm for multiple resources-constrained project. IEEE Conferences, Business and Information Management International Seminar, Wuhan, China, 1, 330-335.
Long, L. D., and Ohsato, A. (2007). Solving the Resource-Constrained project scheduling problem by Genetic Algorithm. Journal of Japan Industrial Management Association, 57(6), 520-529.
Long, L. D., and Ohsato, A. (2008). Fuzzy critical chain method for project scheduling under resource constraints and uncertainty. International Journal of Project Management, 26(6), 688-698.
Newbold, R. C. (1998). Project Management in the Fast Lane-Applying the Theory of Constrains. The St. Lucie Press, Boca Raton.
Newbold, R. C. (2008). The Billion Dollar Solution—Secrets of PROCHAIN Project Management. ProChain Press, Lake Ridge, VA.
ProChain Solutions Inc. (2011). http://www.prochain.com
PMBOK. (2004). Project management body of knowledge. PMI (Project Management Institute), PMI Press, Pennsylvania.
Rand, G. K. (2000). Critical chain: the theory of constraints applied to project management. International Journal of Project Management, 18(3), 173-177.
Realization Technologies Inc. (2011). Resource Library. http://www.realization.com /resource-library.html#casestudies, Accessed March 20, 2011.
Rezaie, K., Manouchehrabadi, B., and Shirkouhi, S. N. (2009). Duration estimation, a new approach in Critical chain scheduling. IEEE Conferences, Modelling & Simulation, Third Asia International Conference, Bali, 481-484.
Steyn, H. (2000). An investigation into the fundamentals of critical chain project scheduling. International Journal of Project Management, 19(6), 363-369.
Steyn, H. (2002). Project management applications of the theory of constraints beyond critical chain scheduling. International Journal of Project Management, 20(1), 75-80.
Trietsch, D. (2005). Why a critical path by any other name would smell less sweet? Towards a holistic approach to PERT/CPM. Project Management Journal, 36(1), 27-36.
Yuji, K. (2010). WA: Transformation management by harmony. Croton-Hudson, North River Press, New York.
Zhao, Z. Y., You, W. Y., and Zuo, J. (2010). Application of innovative critical chain method for project planning and control under resource constraints and uncertainty. Journal of Construction Engineering and Management, 136(9), 1056-1060.

In-Text Citation: (Huang et al., 2014)
To Cite this Article: Huang, C-L., Li, R-K., Tsai, C-H., Chung, Y-C., Hsu, Y-W. (2014). A Study of Using Simulation to Overcome Obstacles that Block the Implementation of Critical Chain Project Management to Project Management Environment. International Journal of Academic Research in Accounting Finance and Management Sciences. 4(1), 30 - 48.